We install all types of partitioning systems for use in commercial or residential developments. Predominantly though, we install metal stud partitions and dry lining products manufactured by British Gypsum, Knauf or Lafarge.
Project : QinetiQ (Malvern)
Client : QinetiQ
Architect : Harrington Design Ltd
Main Contractor : Warings Contractors Ltd
Project Overview
Brief:
New build offices consisting of two four story buildings.
Build new metal stud partitions to form offices. Dryline all external walls and staircases including joint tape finish.
Materials:
Knauf plasterboard products.
<£100,000 | £100,000 - £250,000 | £250,000 - £500,000 |
£500,000 - £750,000 | £750,000 - £1,000,000 | £1,000,000-£2,000,000 |
>£2,000,000 |
Programme:
22 weeks. Workforce between four and thirty-five men.