Safeway (Rushden)  
 
 Click images below to view larger version
Click to expand Click for larger view Click to expand
Click to expand Click to expand Click to expand
 
     
 
Safeway plc  
 
     
 
Safeway In-house Design Team  
 
     
 
PCM Projects Ltd, Hampton-in-Arden  
 
 
 


Brief:
Complete strip out of existing ceilings and bulkheads, conversion of store into mega-store, installation of new ceilings throughout existing sales area and new extension area whilst store operation continued uninterrupted (24 hour opening).

Materials:
SAS system 130 600 x 600mm plain metal ceiling tiles, aluminium Q grid system, feature plasterboard bulkheads, Quinton and Kaines timber ceilings, SAS System 150 1200 x 300mm feature barrel-vaulted ceiling, SAS System 150 600 x 600mm plain metal clip-in tiles.

Contract Value:

< £100,000 £100,000 - £250,000 £250,000 - £500,000

£500,000 - £750,000

£750,000 - £1,000,000 >£1,000,000

Programme:
PHASE 1:
6 weeks commencing with site 'strip out'
(November to December 2001).
PHASE 2: 20 weeks re-fit covered with 24 hour working shifts
(January to May 2002).

Workforce varied between two and thirty-five men depending on requirement.