Brief:
Complete strip out of existing ceilings and bulkheads, conversion
of store into mega-store, installation of new ceilings throughout
existing sales area and new extension area whilst store operation
continued uninterrupted (24 hour opening).
Materials:
SAS system 130 600 x 600mm plain metal ceiling tiles, aluminium
Q grid system, feature plasterboard bulkheads, Quinton and
Kaines timber ceilings, SAS System 150 1200 x 300mm feature
barrel-vaulted ceiling, SAS System 150 600 x 600mm plain metal
clip-in tiles.
Contract Value:
| <
£100,000 |
£100,000
- £250,000 |
£250,000
- £500,000 |
| £500,000
- £750,000 |
£750,000
- £1,000,000 |
>£1,000,000
|
Programme:
PHASE 1: 6 weeks commencing with site 'strip out'
(November to December 2001).
PHASE 2: 20 weeks re-fit covered with 24
hour working shifts
(January to May 2002).
Workforce varied between two and thirty-five
men depending on requirement.
|