Brief:
New build offices for PMAS HQ
Installation of new metal ceilings
throughout office areas; feature waved metal ceiling and plasterboard
feature bulkheads to atrium area.
Materials:
SAS system 130 600 x 600mm plain metal ceiling tiles, standard
T exposed grid system, SAS 600 x 600 system 150 feature wave
ceiling. Plasterboard MF system ceilings and bulkheads.
Contract Value:
| <
£100,000 |
£100,000
- £250,000 |
£250,000
- £500,000 |
| £500,000
- £750,000 |
£750,000
- £1,000,000 |
>£1,000,000
|
Programme:
6 weeks. Workforce between two and six men.
|